DTV TRANSITION STATUS REPORT

PLEASE READ INSTRUCTIONS BEFORE COMPLETING THIS FORM

FOR COMMISSION USE ONLY
FILE NO.

BDTUET - 20081016AEQ

NOTE: Each Licensee/Permittee is responsible for the continuing accuracy and completeness of the information furnished in this Form. Each Licensee/Permittee must update this Form, as necessary, until such Licensee/Permittee reports the completion of its transition (i.e., that it has begun operating its full, authorized facility as defined in the post-transition DTV Table, 47 C.F.R. 73.622(i), and accompanying Appendix B).

SECTION I - GENERAL INFORMATION

Licensee/Permittee Information
1. Legal Name of the Licensee/Permittee
BOARD OF TRUSTEES OF NORTHERN MICHIGAN UNIVERSITY
Mailing Address
WNMU-TV/FM
1401 PRESQUE ISLE

City
MARQUETTE
State or Country (if foreign address)
MI
ZIP Code
49855 - 5301
Telephone Number (include area code)
9062271300
E-Mail Address (if available) 
DBETT@NMU.EDU
Contact Information (if different from licensee/permittee)
2. Contact Representative
JEROLD L. JACOBS, ESQ.
Firm or Company Name
COHN AND MARKS LLP
Mailing Address
1920 N ST., N.W.
SUITE 300

City
WASHINGTON
State or Country (if foreign address)
DC
ZIP Code
20036 - 1622
Telephone Number (include area code)
2022933860
E-Mail Address (if available) 
JEROLD.JACOBS@COHNMARKS.COM
Station / Facility Information
3. FCC Registration Number
0002735751
Call Sign 
WNMU
Facility ID Number
4318
Community of License: City
MARQUETTE

State
MI

Network Affiliation (if applicable)
Satellite?
Yes   No
Purpose of Form:
4.
a. Status Report
b. Update     
c. Amendment
If an amendment, submit as an Exhibit a listing by Section and Question Number the portions of the pending application that are being revised. [Exhibit 1]

SECTION II - CURRENT STATUS

1.
Currently Assigned Channels:
a. NTSC Channel: 13 
b. Post-Transition DTV Channel:  13
c. Pre-Transition DTV Channel (if different from Post-Transition channel.) 33
2.
Relevant FCC File No. for Post-Transition Authorization, if on file with Commission (or indicate "Not Yet Filed"):
FCC File No. BMPEDT- 20080312ACG Not Yet Filed
3.
Current Construction Deadline: 02/17/2009




SECTION III - POST-TRANSITION FACILITY (Complete all items unless otherwise indicated.)

1. Operational Status:
Is the Licensee/Permittee now operating its fully authorized final, DTV (post-transition) facility?
Yes No     (If YES, go to Section V; If NO, go to Item 2.)

2. If Item 1 is NO (i.e., not fully operational), then indicate operational status of final, DTV (post-transition) facility and indicate date Licensee/Permittee expects to begin full, authorized post-transition operations: (check one)
(i)
Licensee/Permittee is operating its post-transition facility pursuant to program test authority; see 47 C.F.R. § 73.1620(a). If checked, indicate date Licensee/Permittee expects to file its license to cover (FCC Form 302) application. Expected Operational Date: 02/17/2009
(mm/dd/yyyy)
(ii)
Licensee/Permittee is operating its post-transition facility pursuant to special temporary authority (STA) or at a reduced facility. If checked, indicate power level and percentage of analog population covered by reduced facility. Power Level
 kW
Population:
 %
(iii)
Licensee/Permittee is not operating its post-transition facility.
3. Construction Status:
Has the Licensee/Permittee completed construction of its final, DTV (post-transition) facility?
Yes No     (If YES, skip Items 4-5 and go to Item 6(a); If NO, go to Item 4.)

4. If Item 3 is NO (i.e., not fully constructed), then indicate construction status of final, DTV (post-transition) facility and indicate date Licensee/Permittee expects to complete construction: (check all that apply)
(i) Licensee/Permittee has not begun construction of its post-transition facility. Expected Construction Date:
02/17/2009
(mm/dd/yyyy)
(ii) Licensee/Permittee is now constructing its post-transition facility.
(iii) Licensee/Permittee has constructed a reduced post-transition facility and additional construction is needed to complete Licensee/Permittee's fully authorized facility.
5. Construction Permit Status:
Does the Licensee/Permittee hold a license or construction permit for its final, DTV (post-transition) facility?
Yes No     (If YES, go to Item 6(a); If NO, skip Item 6(a) and go to Item 6(b).)

6.
a. Does the Licensee/Permittee need to modify its license or construction permit in order to match the post-transition facilities defined for the Licensee/Permittee in the new DTV Table of Allotments, 47 C.F.R. § 73.622(i), as adopted in the Seventh Report and Order in MB Docket No. 87-268?
Yes No     (If YES, go to 6(b); If NO, skip Item 6(b) and go to Section IV.)

b. Has the Licensee/Permittee filed an application for a new or modified construction permit for its final, DTV (post-transition) facility? (If YES, indicate relevant FCC File No. and date filed; If NO, indicate date Licensee/Permittee expects to file such application.) (NOTE: To qualify for expedited processing, the Licensee/Permittee must file its application within 45 days of the effective date of the Report and Order in the Third DTV Periodic Review proceeding, MB Docket No. 07-91, as well as meet other criteria established in that proceeding.)
Yes
FCC File No.
- Filing Date: (mm/dd/yyyy)
No
Expected Filing Date:
(mm/dd/yyyy)

SECTION IV -- ADDITIONAL STEPS NEEDED TO COMPLETE CONSTRUCTION (For Licensees/Permittees that are not fully constructed or operational.)

At present, Licensee/Permittee has the following needs that must be addressed before it can fully construct and/or operate its final, DTV (post-transition) facility: (check all that apply and for all checked responses, describe issue and estimate date of resolution. If necessary, provide an explanation or attach an Exhibit). [Exhibit 2]
(1) Licensee/Permittee needs to obtain FCC action on a pending application. (If checked, indicate date filed and relevant FCC File No.)
FCC File No. -

Date filed: (mm/dd/yyyy)

(2) Licensee/Permittee needs to obtain international government clearance for its post-transition facility.
(3) Licensee/Permittee needs to obtain FAA approval for its post-transition facility.
(4) Licensee/Permittee needs to obtain state or local governmental approval (e.g., zoning) for its post-transition facility.
(5) Licensee/Permittee needs to obtain, adjust and/or install equipment for its post-transition facility. (If checked, specify need below and indicate when equipment was ordered and expected delivery date.)
(1) New antenna.
(2) Adjust or install antenna (except for side-mount issue).
(3) Switch side-mounted DTV antenna with top-mounted analog antenna.
(4) New transmitter.
(5) Adjust or install transmitter.
(6) General installation of equipment requiring hiring of a tower crew.
(7) Other equipment needs. (If checked, specify.)
(6)
Licensee/Permittee needs to change its tower location or construct a new tower.
(7) Licensee/Permittee needs to coordinate its transition with other broadcast stations. (If checked, specify Call Signs of those other stations.)
(8) Licensee/Permittee has other needs that must be addressed before it can fully construct and operate its post-transition facility. (If checked, explain.)

SECTION V -- ANALOG SERVICE

Status of Analog Service. (Check one.) If necessary, provide an explanation or attach an Exhibit. Note: Full-power television broadcast stations must cease broadcasting in analog as of the transition date (i.e., June 12, 2009), as required by statute; see 47 U.S.C. § 309(j)(14). [Exhibit 3]
(1) Licensee/Permittee will continue to provide full, authorized analog service until the transition date.
(2) Licensee/Permittee has obtained FCC approval to reduce its analog service prior to the transition date. If checked, indicate relevant FCC File No., date reduced service will begin, power level and percentage of population covered by Licensee/Permittee's analog service.
(3) Licensee/Permittee has obtained FCC approval to terminate its analog service prior to the transition date. If checked, indicate relevant FCC File No. and date service will cease.
(4) Licensee/Permittee has filed an application with the FCC requesting approval to reduce its analog service prior to the transition date. If checked, indicate relevant FCC File No., proposed date reduced service would begin, proposed power level and percentage of population that would be covered by Licensee/Permittee's proposed reduced analog service.
(5) Licensee/Permittee has filed an application with the FCC requesting approval to terminate its analog service prior to the transition date. If checked, indicate relevant FCC File No. and proposed date service will cease.


SECTION VI -- DTV TRANSITION PLAN For Licensees/Permittees that are not fully constructed or operational.

Licensee/Permittee must describe in detail its plans for ceasing analog broadcasting by the June 12, 2009 transition date and for completing construction of its post-transition facility by the deadline. For example, plan must include a detailed time line of the Licensee/Permittee's plans to complete construction and any necessary testing of the Licensee/Permittee's full, authorized post-transition facility. [Exhibit 4]

SECTION VII -- ANTI-DRUG ABUSE ACT CERTIFICATION

Filer certifies that neither it nor any party to the form is subject to denial of federal benefits pursuant to Section 5301 of the Anti-Drug Abuse Act of 1988, 21 U.S.C. Section 862. Yes No

SECTION VIII -- CERTIFICATION

I certify that the statements in this application are true, complete, and correct to the best of my knowledge and belief, and are made in good faith. I acknowledge that all certifications and attached Exhibits are considered material representations. I hereby waive any claim to the use of any particular frequency as against the regulatory power of the United States because of the previous use of the same, whether by license or otherwise, and request an authorization in accordance with this application. (See Section 304 of the Communications Act of 1934, as amended.)

Typed or Printed Name of Person Signing
THERESA NEASE
Typed or Printed Title of Person Signing
SECRETARY OF THE BOARD OF TRUSTEES
Signature
Date
10/16/2008

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1)), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503).



Exhibits
Exhibit 2
Description:
EXH. 2 ADDITIONAL STEPS NEEDED

IN ADDITION TO ALL OF THE EQUIPMENT ITEMS LISTED IN SECTION IV(5) TO BE OBTAINED, ADJUSTED, AND/OR INSTALLED, WNMU-DT MUST ALSO OBTAIN A MICROWAVE LINK AND A TRANSMISSION LINE.

Attachment 2


Exhibit 3
Description:
EXH. 3 ANALOG SERVICE TERMINATION

DUE TO THE MANUFACTURER'S INABILITY TO INSTALL WNMU-DT'S FINAL DTV ANTENNA PRIOR TO THE WINTER OF 2008/2009, WNMU WILL NOT BE ABLE TO OPERATE ITS NEW DTV ANTENNA UNTIL MAY 2009. THEREFORE, WNMU WILL NOT NEED TO REDUCE POWER ON ITS ANALOG FACILITY UNTIL FERUARY 17, 2009. AT THAT TIME, WNMU WILL USE THE STA AUTHORITY THAT IT RECEIVED ON SEPTEMBER 22, 2008 TO OPERATE ITS NEW DIGITAL TRANSMITTER WITH ITS OLD ANALOG ANTENNA UNTIL MAY 2009 AS DESCRIBED IN EXHIBIT 4 BELOW.

Attachment 3


Exhibit 4
Description:
EXH. 4 DTV TRANSITION PLAN

WNMU WILL BE IMPLEMENTING A PHASED CONSTRUCTION OF ITS FINAL DIGITAL FACILITY.

NOVEMBER 2008. REPLACEMENT OF THE STATION'S ANALOG STL MICROWAVE WITH NEW DIGITAL RADIOS. THE STATION CURRENTLY HAS A DIGITAL STL TO ITS FIRST MICROWAVE HOP WHERE WNMU-DT IS LOCATED. ANALOG RADIOS ON THE FINAL TWO HOPS TO THE STATION'S ELY LOCATION TRANSMITTER MUST STILL BE REPLACED TO FACILITATE THE SWITCH FROM WNMU'S ANALOG TRANSMITTER TO DIGITAL.

WINTER 2008/2009. WNMU-DT WILL INSTALL A NEW 2.5 KW 8VSB DIGITAL TRANSMITTER AT ITS ELY TRANSMITTER SITE TO SWITCH ON LINE ON FEBRUARY 17, 2009.

MAY 2009. WNMU-DT WILL REPLACE THE EXISTING ANTENNA AT ITS ELY TRANSMITTER SITE WITH A NEW DIELECTRIC TW-9B13 ANTENNA AS SPECIFIED IN THE CONSTRUCTION PERMIT. WNMU-DT WILL ALSO REPLACE ITS 6 1/8 INCH TRANSMISSION LINE WITH 4 1/16 INCH LINE. THIS WORK WILL NEED TO BE DONE AFTER THE WINTER SEASON BECAUSE OF EXTREME WEATHER AT THIS LATITUDE IN MICHIGAN'S UPPER PENINSULA. INITIAL PLANS TO INSTALL THIS EQUIPMENT IN THE FALL OF 2008 HAVE BEEN DELAYED DUE TO THE INABILITY OF THE MANUFACTURER TO DELIVER THE ANTENNA BEFORE WINTER. ANTENNA AND TRANSMISSION LINE REPLACEMENT WILL REQUIRE WNMU TO BE OFF THE AIR FOR A PERIOD OF UP TO TWO WEEKS DURING THAT TIME. WE WILL CONTINUE TO PROVIDE PROGRAMMING TO CHARTER CABLE VIEWERS VIA FIBER LINK.

NOTE: ON SEPTEMBER 22, 2008, THE FCC GRANTED OUR JULY 23, 2008 STA REQUEST FOR A PHASED FINAL DTV IMPLEMENTATION FOR WNMU-DT (FILE NO. BEDSTA-20080723ACM)TO OPERATE ITS NEW DIGITAL FACILITY FROM FEBRUARY 17, 2009 UNTIL MAY 2009 WITH ITS CURRENT ANALOG ANTENNA. THE OLD ANTENNA HAS A HIGHER GAIN THAN THE NEW ONE AND WILL REQUIRE A REDUCED TRANSMITTER TPO. ALSO THE OLD ANTENNA HAS A SLIGHTLY HIGHER CENTER OF RADIATION BECAUSE OF ITS LENGTH SO WE WILL NEED TO REDUCE OUR ERP DURING THIS PHASE OF OUR CONSTRUCTION.

ALL NECESSARY TESTING FOR PROOF OF PERFORMANCE WILL BE COMPLETED BY THE MANUFACTURER'S INSTALLATION TEAMS AT THE TIME OF INSTALLATION.

Attachment 4